Apollo's New Design Updates

Apollo's New Design Updates
CARISSA HOPKINS-HOEL

Construction at Apollo will take place in phases from spring 2026 through summer 2028. 

Early work includes building a new ambulance bay, EMT classroom and storm shelter, followed by renovations to locker rooms, collaboration areas and fitness spaces. Construction of the secure entrance will begin when the storm shelter is complete per building code. A new multipurpose indoor athletics center will also begin construction in spring 2026 and is expected to be completed by spring 2027.

Subsequent phases will add new science, culinary, communications and computer science labs, along with updated commons, cafeteria and administrative areas. 

The final stage will complete the front entrance, arts and music spaces, and remaining classroom renovations, with the full project scheduled for completion before the start of the 2028–29 school year